Small Renewable Energy Program Proposed Privatisation of Napunggok Hydroelectric Project, Kota Belud, Sabah

Client:

Actual Triumph Sdn Bhd

Description of Project:

The proposed project is a mini hydro scheme with a potential capacity of up to 6MW. The water will be conveyed through a 3.6km headrace pipeline and a 400m penstock to the power station sited on the left bank of Sg. Wariu with effective head of 175m. The transmission line will be a 33kV aerial cable using the existing poles to Kota Belud sub station.

Services Provided:

Hydrological analysis and desktop study of the proposed project. The study is based on the hydrological analysis the following were determined: type of scheme to be developed-storage or run of the river, estimates energy generation and estimate project cost.

Back
Content Management Powered by CuteNews

 

Top